Skip to main content
Commercial downtime is expensive. Get same-week scheduling: 408-614-4451

Infrastructure · Commercial EV Fleet Charging

The utility builds to the meter. We build from the meter to your fleet.

Customer-side commercial EV fleet charging across Santa Clara County: load study, service and switchgear, feeders and trenching, EVSE, and network commissioning. Realistic utility timelines, an honest read on which programs are actually open, and no OEM lock-in.

California electrical contractor
C-10 #1144031California electrical contractor
Typical utility fleet-program timeline
9-13 moTypical utility fleet-program timeline
Code-documented on every install
NEC 625Code-documented on every install
Vendor-neutral EVSE, no network lock-in
OCPP 1.6 / 2.0.1Vendor-neutral EVSE, no network lock-in

Quick answer

Your utility builds the make-ready up to the meter. Everything past it is the electrical scope our team carries: an NEC 220 and Article 625 load study, service and switchgear work, feeders, trenching, EVSE, and network commissioning. Plan on roughly 9 to 13 months where a utility fleet program applies and a 2 to 4 month behind-the-meter construction window. PG&E's EV Fleet program is fully subscribed (its waitlist closed June 30, 2026), so most 2026 depots run as a standard service extension. Sites in Silicon Valley Power territory can still pursue the SVP EV Charging Station Incentive (up to $150,000 per site, funds verified at estimate). C-10 #1144031.

Customer-side scope

What the behind-the-meter scope actually covers

Fleet charging quotes are hard to compare because contractors draw the scope line in different places. Here is where ours sits, item by item, from the load study through the closeout package.

Commercial EV fleet charging scope items and permit requirement
Scope itemWhat it involvesPermit
Fleet load study & service capacity analysisNEC 220 connected-load math plus Article 625 continuous-load sizing at 125%No
Service, switchgear & distribution upgradeNew service section, panelboards, and feeders sized to the final port countYes
EVSE branch circuits & feedersConductors, overcurrent protection, and disconnects per NEC Article 625Yes
Trenching, conduit & pull boxesParking-area routing, sweeps, fire-access clearances, and civil coordinationYes
EVSE mounting, termination & commissioningBollard or wheel-stop protection, torque-documented terminations, port testingYes
Automatic load management (ALMS)Programmed simultaneous-power limits, shown on the plans and validated at finalYes (shown in plans)
OCPP onboarding & closeout packageAs-built drawings, equipment data sheets, network credentials, warranty paperworkNo
Utility coordination (PG&E, SVP, CPAU)Application, single-line, load schedule, and milestone tracking to energizationCoordinated

The incentive landscape

Honest status on every fleet-charging program in our footprint

Most contractors lead with “claim your rebate” framing. The mid-2026 reality is plainer than that. PG&E's EV Fleet program is fully subscribed with the waitlist closed, and Silicon Valley Power's commercial fleet rebate is between funding cycles. Here is what is open, what closed, and what your project plan should assume.

PG&E EV FleetFully subscribed, waitlist closed

Not accepting new applications; waitlist closed Jun 30, 2026

PG&E's EV Fleet program is fully subscribed. The waitlist stopped accepting applications on June 30, 2026, and the program is not accepting new applications. Participants commit to a 5-year vehicle and charging plan, a 10-year operating commitment, and 5 years of EV usage data reporting. PG&E builds the make-ready up to the meter; our team handles every component on the customer side. Projects starting now generally run as standard service extensions instead, which is not a worse path, just a different one to plan around.

SVP Commercial ZEV Fleet RebateClosed; the Jul 1, 2026 check-back passed

Closed to new applications since Dec 22, 2025

Silicon Valley Power's Commercial Zero-Emission Vehicle Fleet Rebate stopped accepting new applications on December 22, 2025. SVP territory is the City of Santa Clara only. The July 1, 2026 check-back date has passed with no relaunch announced, so we re-verify status at estimate. Listed here so fleet operators in SVP territory know not to build a mid-2026 deployment budget around it.

SVP EV Charging Station IncentiveListed as available (the one open local incentive)

Up to $150,000 per site; verify remaining funds at estimate

Silicon Valley Power's Level 1 and Level 2 charging incentive for commercial and multifamily sites, up to $150,000 maximum per site, is listed as available. Equity-eligibility increases stack on the base cap. It applies to sites inside SVP electric territory, which is the City of Santa Clara only, and funding can draw down without notice, so we verify remaining funds with SVP at your estimate before you count it in the budget.

CalEVIP Fast Charge CaliforniaPrior rounds closed, new statewide windows announced

Windows open Oct 7, 2026 and Feb 24, 2027

The prior CalEVIP Fast Charge California Project application window closed January 29, 2026, and the Golden State Priority Project allocation has been closed since its March 2024 funding-notification milestone. The CEC announced a new $55.2M CalEVIP round on May 28, 2026, with two statewide application windows opening October 7, 2026 and February 24, 2027. It targets publicly accessible DC fast charging (150 kW and up) at ready-to-build sites, not typical Level 2 depot charging, so it fits fleet hosts adding public fast-charge capacity. We map shovel-ready sites to the window that fits.

Federal 48E (storage ITC)Preserved for battery storage

Full credit for construction beginning through 2033

The Clean Electricity Investment Tax Credit (48E) for battery storage was preserved under the 2025 federal budget law: full value for construction beginning through 2033, then a phase-down (22.5% in 2034, 15% in 2035). Standalone depot storage that firms a fleet-charging site against demand charges and utility-timeline risk is the durable federal play here. It is an IRS credit on the site owner's return, not a rebate we administer and not a guaranteed dollar figure. Post-2025 content-sourcing (FEOC) rules apply, so we point you to your CPA to size it against your project.

Key dates

  • Dec 22, 2025 SVP commercial ZEV fleet rebate stopped accepting applications
  • Jun 30, 2026 PG&E EV Fleet waitlist closed (fully subscribed)
  • Aug 31, 2026 CARB Advanced Clean Fleets amendments OAL submission deadline
  • Oct 7, 2026 CalEVIP Fast Charge California window opens
  • Jan 2027 State and local government fleets hit the 50% ZEV purchase target
  • Feb 24, 2027 Second CalEVIP statewide application window opens
Map your project to the calendar

What is actually open

Five live pathways worth building your plan around

Not every door closed in late 2025. Flex Connect, a standard service extension, HVIP on the vehicle side, LCFS revenue once chargers are dispensing, and the 2025 CALGreen new-construction trigger are all live, and each one shapes the project plan differently.

PG&E Flex Connect

Conditional-use grid connection that can compress site-energization timelines when the existing service has headroom. PG&E reported approximately 35 site analyses per quarter in 2025, with about 5 sites operational mid-2025 and a 10-site target by year-end 2025. PepsiCo's Fresno site unlocked 4.5 MW of enhanced capacity 18 months early through the program. Best fit for fleet sites where a standard utility program timeline does not pencil.

Standard service extension (Rule 15 / Rule 16, plus Rule 21 where storage exports)

With the PG&E EV Fleet program closed, most 2026 depot projects run as an ordinary service extension: a load-addition request, a distribution or service line extension under the utility line-extension tariffs, and a construction milestone we track to energization. Where the depot also adds on-site solar or battery storage that can export, a Rule 21 generator interconnection application runs in parallel. Our team prepares the single-line, the load schedule, and the application package, and keeps both tracks moving against the same construction date.

HVIP (vehicle-side)

California's Hybrid and Zero-Emission Truck and Bus Voucher Incentive Project (HVIP) is open and funding voucher requests first-come, first-served in mid-2026, with funding released in waves that can fully reserve without notice. Published amounts run from $7,500 (Class 2b) up to $552,000 (fuel-cell transit buses with adders) and depend on the specific vehicle and catalog eligibility. Treat any figure as 'up to', not guaranteed. A separate LCFS-funded point-of-sale commercial truck rebate also opened June 26, 2026; stacking rules with HVIP are still settling, so we verify current terms before you count on either. Both are vehicle-side. We coordinate with your vehicle-acquisition timeline so charging is energized before the trucks arrive.

LCFS revenue

California's Low Carbon Fuel Standard generates credits for electricity dispensed to EVs, monetized through an aggregator at a credit price that moves weekly. It hovered near $66 per metric ton in spring 2026, so we model a range, never a fixed payout. The Fast Charging Infrastructure (FCI) pathway adds up to 10 years of capacity-based credits, but it applies to networked DC fast chargers permitted on or after January 1, 2022 only (20% multiplier for public or shared access, 10% for private) with a December 31, 2030 first-come deadline on the LMD-FCI allocation. Level 2 depot charging does not earn FCI capacity credits (it uses the separate base LCFS pathway). The FCI allocation is capped at 2.5% of statewide LCFS deficits with a 0.5% per-entity sub-cap, and from the 2026 data year forward all transactions require third-party ARB-accredited verification.

CALGreen 2025 (new-construction trigger)

The 2025 CALGreen Section 4.106.4.2.6 requires new hotels and motels to provide EV-ready receptacle infrastructure on 40% of parking spaces and installed Level 2 chargers on 25% of spaces, which is 65% of stalls with EV provision in total. Automatic Load Management Systems are permitted, with a 3.3 kW per-connected-charger simultaneous-power floor. New non-residential construction and major tenant improvements built or permitted in 2026 are inside this mandate, so the charging scope belongs in the plan set from the first submittal, not as a change order after framing.

Who we serve

Six fleet-charging segments across Santa Clara County

Every fleet segment has its own duty cycle, procurement calendar, and grid constraint. We do not treat last-mile delivery like school-bus depot make-ready. The site walk maps the customer-side scope to how your vehicles actually run.

Last-mile delivery fleets

Parcel carriers, regional couriers, and grocery or pharmacy delivery. High-cycle return-to-base operations with overnight depot charging. Load-management software pairs well with Level 2 plus a small number of DC fast ports for mid-shift top-up, which keeps the service size down.

Transit & paratransit

VTA broke ground on the Cerone Microgrid Project at its Cerone Bus Division in September 2025: 1.5 MW of rooftop solar PV plus 1 MW / 4 MWh of battery storage for 35 battery-electric buses scheduled for 2026 delivery. Public-sector procurement, Buy America considerations, and NFPA 70E discipline at every step.

Municipal & nonprofit

Cities, counties, special districts, and 501(c)(3) operators. State and local government fleets remain on a 50% ZEV-purchase target effective January 2027 and 100% ZEV by 2030 per the September 2025 CARB Advanced Clean Fleets amendments. Public-sector demand for fleet-charging make-ready is durable on that timeline, and the work is often prevailing-wage.

School districts

The federal EPA Clean School Bus program is paused and under revamp, and BAAQMD's dedicated bus-charger solicitation has closed, but electric-bus depot make-ready stays fundable in-territory through Carl Moyer, AB 617 Community Air Protection, and California HVIP. We point districts to the channels that are actually live, and phase work around K-12 procurement calendars and summer-break execution windows.

Contractor & utility fleets

Mixed-duty trucks, service vans, and lift-gate equipment. Sub-metered depot charging with telematics integration for fleet-management reporting, so per-vehicle energy cost is attributable. C-10 #1144031 sign-off on every install.

Hotels, multifamily & corporate campus

EV charging as a tenant-attraction and guest-loyalty amenity. The 2025 CALGreen code now obligates hotels and motels on new construction; existing properties retrofit on their own timeline. Multifamily and mixed-use sites in Silicon Valley Power territory fall under the SVP per-port incentive structure.

Code, standards, permits

Every install documented to NEC Article 625 and NFPA 70E

Commercial EV charging is a code-heavy install. Article 625 governs the branch-circuit math, CALGreen governs new-construction provisioning, Chapter 11B governs the accessible stalls, and NFPA 70E governs the work practices: de-energized first, with live work only where a shutdown genuinely is not possible and documented when it is. We document all of it on every project.

Code, standards, and permit requirements for commercial EV charging
C-10 requirementCalifornia's Contractors State License Board requires a C-10 Electrical Contractor license for every EV charging equipment installation, including Level 2 ('Class 2' is a lay term for the same equipment) and DC fast charging. Cali Rollin Electric is C-10 #1144031.
NEC Article 625Article 625 of the National Electrical Code governs EV charging system installation: branch-circuit and feeder calculations at 125% of continuous load, disconnect requirements, ventilation provisions, and equipment marking. Every install we do is calculated and documented to Article 625.
Voltage architectureLevel 2 single-phase (7.2 to 19.2 kW per port) for typical depot and workplace overnight charging. DC fast charging on three-phase 480V for opportunity charging, medium- and heavy-duty vehicles, and bus transit. We size the service, coordinate the transformer, and document the load schedule.
Open Charge Point ProtocolOCPP 1.6 and 2.0.1 specified across the EVSE brands we install (ChargePoint, ABB, Wallbox, FLO, and others). OCPP is the open, vendor-neutral protocol, so there is no lock-in to a single network operator. We confirm OCPP compatibility at spec, before anything is ordered.
Load management (ALMS)An Automatic Load Management System lets a site run more ports than raw service capacity would allow by capping simultaneous draw. It has to be modeled at design, drawn on the plans, and validated at commissioning, and CALGreen sets a 3.3 kW per-connected-charger floor where that mandate applies. Done right it is often the difference between a straightforward install and a full service upgrade.
AccessibilityWhere EV charging stations are provided at a commercial site, California Building Code Chapter 11B sets the accessible and van-accessible stall counts, the clearances, and the signage. Plan check reviews it, so the stall layout and the electrical layout have to be coordinated before submittal, not after the trench is dug.
NFPA 70EDe-energized is the default on every panel and switchgear interaction, and where a shutdown genuinely is not possible the work runs to NFPA 70E. Each task gets a documented arc flash risk assessment and shock risk assessment, and the required protection is carried into a written job safety plan and briefed before anyone opens anything. Whether that protection is expressed as an incident energy figure or as a PPE category depends on which method the equipment is assessed under, and the two are never mixed on the same gear. NFPA 70E is functionally mandatory on this work through the Cal/OSHA electrical safety-related work practice requirements.
PermitsPlans-based electrical permits are required for commercial Level 2 (over the over-the-counter threshold) and for all DC fast charging in every Santa Clara County jurisdiction. Plans are reviewed against California Electrical Code Article 625, CALGreen, and the local municipal electrical code chapter. Commercial permit fees typically run $750 to $2,500 or more depending on jurisdiction and job valuation, because each jurisdiction computes the electrical fee on its own basis, inspection time in San Jose, a percentage of the building permit fee in the County, device count or floor area in most other cities.

Multi-utility footprint

  • PG&E: 13 of the 15 Santa Clara County cities
  • Silicon Valley Power: City of Santa Clara only
  • City of Palo Alto Utilities: Palo Alto only

Each utility runs its own interconnection process, tariff, and incentive timeline. We map your site to the right utility on the walk, and pull the current tariff before pricing.

Discuss your site

Timeline reality

Ranges from the AHJ and the utility, not from marketing copy

Fleet charging is a long-pole-item project. The vehicle side only moves fast if the charging side was thought through first. These are the ranges that show up on real Santa Clara County projects, and the reason we start the utility and permit tracks before anything is ordered.

Typical commercial EV fleet charging project durations
Utility fleet-program application to energization9 to 13 months
Standard plan review, largest county jurisdictions40+ weeks
Expedited plan review (small projects)10 to 12 weeks
Third-party express plan check2 to 3 business days
Typical Santa Clara County city electrical plan review2 to 8 weeks
Service-constrained site needing a new transformer12 to 24+ months
Behind-the-meter construction window (typical)2 to 4 months
Inspection, commissioning & OCPP onboarding1 to 4 weeks

The long pole

  • Transformer headroom: Site-specific, and the single biggest schedule risk
  • Utility program milestone: 9 to 13 months of coordination when a program applies
  • Plan check: 40+ weeks standard in the largest jurisdictions, 10 to 12 expedited
  • Long-lead switchgear: Ordered against the utility construction milestone, not the permit date

Service-constrained sites that need a new transformer can stretch to 12 to 24+ months. Flex Connect and a load-management design are the two tools we look at first to compress that window where service headroom exists.

C-10 #1144031 ↗Insured & Bonded15+ years in the tradeServing all 15 Santa Clara County cities

How a fleet-charging project runs

Eight steps: walk, plan, apply, permit, procure, install, inspect, register

Fleet charging looks simple from the outside and has eight serial moving parts on the inside. Our process front-loads the long-pole items (utility application, transformer assessment, permit submittal) so the install itself runs clean and the trucks arrive to energized ports.

01

Site walk & load study

1 to 3 days

Existing service capacity, panel and switchgear condition, transformer headroom, parking circulation, fire-access clearances, and conduit routing. We bring the current tariff in writing rather than quoting from memory.

02

Fleet plan & EVSE specification

1 to 3 weeks

Vehicle profile to port count to per-port kW to feeder size. OCPP-compatible EVSE specified to the project requirements (ChargePoint, ABB, Wallbox, FLO, and others), never locked to one OEM. Load management modeled wherever simultaneous power would exceed the incoming service.

03

Utility application & interconnection

Varies by program

Flex Connect where service headroom exists, or a standard line- and service-extension application. Our team prepares the application, the single-line, and the load schedule, then tracks utility milestones through to energization.

04

Permit submission & plan check

Varies by AHJ

Plans drawn to California Electrical Code Article 625 and the 2025 CALGreen provisions, submitted to whichever Santa Clara County permit center has jurisdiction. Plan-check responses are part of our scope, not a task we hand back to you.

05

Procurement & delivery staging

2 to 8 weeks lead time

EVSE, switchgear, panels, conduit, and conductors. Long-lead items (transformers, main-breaker-rated gear) are ordered against the utility construction milestone so equipment does not sit in a yard collecting storage charges.

06

Installation

2 to 4 months typical

Trenching, conduit, conductor pulls, panels, EVSE mounting and termination, and OCPP onboarding. Gear comes down before we work in it, any step that genuinely cannot be de-energized is planned and documented to NFPA 70E, and cutovers are scheduled around your operating hours.

07

Inspection & commissioning

1 to 4 weeks

Electrical final, network backend onboarding, load-management profile validation, and dispatch and revocation testing on each port. Closeout package: as-built drawings, equipment data sheets, network credentials, and warranty paperwork.

08

LCFS pathway registration (optional)

6 to 12 weeks

For sites pursuing LCFS revenue, we hand the metering and reporting profile to your LCFS aggregator. ARB-accredited third-party verification is required from the 2026 data year forward, so the metering has to be right the first time.

Why Cali Rollin Electric

Customer-side specialists for commercial fleet charging

The customer-side scope on a fleet-charging project is a long list of code, utility coordination, permit, switchgear, and network work. Plenty of contractors will hang EVSE on a wall. Fewer will sit on a 9 to 13 month utility milestone schedule and document every step to NEC Article 625. That gap is where our commercial fleet practice was built.

C-10 #1144031. 15+ years in the trade. Gear de-energized first, live work planned to NFPA 70E. (408) 614-4451.

Customer-side C-10 specialist

The utility builds to the meter. We build from the meter: load study, feeders, panels, EVSE, network onboarding, and the closeout package.

Brand-agnostic EVSE

We install and commission the hardware your fleet standardizes on, including Tesla Wall Connector and Universal Wall Connector, ChargePoint, and other OCPP-compatible EVSE.

Realistic utility timelines

You hear the 9 to 13 month coordination reality before you sign, not after the permit is stuck behind a transformer order.

Honest incentive landscape

PG&E EV Fleet is fully subscribed and SVP's commercial fleet rebate is between funding cycles. We map your project against what is actually open, not against an aggregator's outdated list.

Brand-agnostic EVSE

ChargePoint (headquartered here in Santa Clara County), ABB, Wallbox, FLO, and others. OCPP-compatible install means no network-operator lock-in.

15 Santa Clara County cities

Every incorporated city in the county. We have filed plans at each permit office and know who asks for what.

Verified reviews

See what our commercial clients are saying about us

★★★★★

Frequently asked questions

Commercial EV fleet charging: FAQ

What does commercial EV fleet charging involve in Santa Clara County?

Commercial EV fleet charging pairs utility make-ready infrastructure with behind-the-meter EV supply equipment installed by a C-10 electrical contractor. The utility builds and owns the infrastructure up to your meter; everything past the meter (load calculations, service and switchgear work, feeders, trenching, EVSE, commissioning, and network onboarding) is the electrical contractor scope. On the program side the 2026 picture is specific: PG&E EV Fleet is fully subscribed and its waitlist stopped accepting applications June 30, 2026, and in Silicon Valley Power territory (the City of Santa Clara) the Commercial Zero-Emission Vehicle Fleet Rebate closed December 22, 2025 with its July 1, 2026 check-back date passed and no relaunch announced. SVP does still list its EV Charging Station Incentive for commercial and multifamily sites, up to $150,000 per site, and we verify remaining funds at estimate. Cali Rollin Electric (C-10 #1144031) installs the customer-side infrastructure across all 15 cities in Santa Clara County.

Is the PG&E EV Fleet program accepting new applications, and who does the work?

PG&E EV Fleet is fully subscribed and is not accepting new applications. The waitlist stopped accepting applications on June 30, 2026. Participants already enrolled commit to a 5-year vehicle and charging plan, a 10-year operating commitment, and 5 years of EV usage data reporting. PG&E builds and maintains the infrastructure up to the meter; the customer-side design, installation, and commissioning from meter to charger is done by a C-10 electrical contractor. Cali Rollin Electric is C-10 #1144031. With the program closed, most fleet sites starting now run as a standard load addition and service extension, which we handle the same way: application, single-line, load schedule, and milestone tracking to energization.

What is the role of the electrical contractor when the utility builds the make-ready?

On a to-the-meter utility program, the utility designs, builds, owns, and maintains all electrical infrastructure up to the customer meter. Everything on the customer side of that meter belongs to the C-10 electrical contractor: NEC 220 and Article 625 load calculations, panel and service upgrades, conduit and trenching, EVSE mounting and commissioning, permit close-out, and ongoing maintenance. The practical value is in the seam between the two. Our team sequences the customer-side scope against the utility make-ready milestone so the trenching, the gear delivery, and the utility construction date line up instead of colliding, and we select from the approved EVSE vendor list where a program requires one.

Do you need a C-10 contractor for Level 2 EV fleet charging installation in California?

Yes. California's Contractors State License Board requires a C-10 Electrical Contractor license for EV charging equipment installation, including Level 2 fleet chargers. ('Class 2' is a lay term for Level 2, the same equipment, roughly 7.2 to 19.2 kW per port.) Cali Rollin Electric holds C-10 #1144031, with 15+ years in the trade installing commercial EV charging across Santa Clara County. Verify the license number directly with CSLB before you sign with anyone, on this project or any other.

What permits are required for a commercial fleet EV charging installation?

Every Santa Clara County jurisdiction requires a plans-based electrical permit for commercial Level 2 charging above the over-the-counter threshold and for all DC fast charging. Plan review runs against California Electrical Code Article 625, the CALGreen provisions that apply to the building, the accessible-stall requirements in California Building Code Chapter 11B, and the local municipal electrical code chapter. Budget $750 to $2,500 or more for the permit depending on jurisdiction and job valuation, because each jurisdiction computes the electrical fee on its own basis, inspection time in San Jose, a percentage of the building permit fee in the County, device count or floor area in most other cities. Our team coordinates plan submission, plan-check responses, and inspection scheduling on every project, so the correction cycle does not land on your facility staff.

Who installs commercial EV chargers across Santa Clara County?

Commercial EV charger installation has to be performed by a C-10 electrical contractor in every Santa Clara County city. Cali Rollin Electric (C-10 #1144031, 408-614-4451) serves all 15 cities in the county: San Jose, Sunnyvale, Santa Clara, Mountain View, Cupertino, Palo Alto, Los Altos, Los Altos Hills, Los Gatos, Saratoga, Campbell, Monte Sereno, Milpitas, Gilroy, and Morgan Hill. Our team carries 15+ years in the trade and handles the full customer-side scope from load calculations through permit close-out and network commissioning.

Does the 2025 CALGreen code require EV charging at new commercial construction?

Yes. The 2025 CALGreen code (Section 4.106.4.2.6, Hotels and Motels) requires new hotels and motels to provide EV-ready receptacle infrastructure on 40% of parking spaces plus installed Level 2 chargers on 25% of parking spaces, totaling 65% of stalls with EV provision. Automatic Load Management Systems are permitted, with a 3.3 kW per-connected-charger simultaneous-power floor. New non-residential construction and major tenant improvements permitted in 2026 fall inside this mandate, which is why the charging scope belongs in the first plan submittal rather than a change order after framing.

Which incentives are still available for commercial EV fleet charging in 2026?

The honest 2026 picture is program by program. Locally, the one open incentive in our footprint is Silicon Valley Power's EV Charging Station Incentive for commercial and multifamily sites, up to $150,000 per site, available inside SVP electric territory (the City of Santa Clara) with funding that can draw down without notice. Federally, the 48E Clean Electricity Investment Tax Credit for battery storage was preserved (full value for construction beginning through 2033), which is useful for depot storage that firms a fleet site against demand charges, and it is an IRS credit on the owner's return, so we point you to your CPA instead of promising a figure. On the vehicle side, California HVIP vouchers are open first-come. Once DC fast chargers are dispensing, LCFS credits generate ongoing per-kWh revenue through an aggregator. We map your specific site against what is actually open, never against an aggregator's outdated list.

Can a site add fleet charging without upgrading the electrical service?

Often, yes, and it is the first thing we test because it is usually the cheapest path. An Automatic Load Management System caps the total simultaneous draw across the ports, so a site can run more chargers than raw service capacity would otherwise support by spreading the energy across the overnight dwell window. Fleets that return to base and sit for eight or ten hours are ideal candidates. We model it against your real duty cycle: vehicle count, battery sizes, arrival and departure times, and the energy each truck actually needs before its next shift. Where the math does not close (a short dwell window, mid-shift charging, or a service already near its demand limit), we tell you that up front and price the service upgrade instead of selling a load-management scheme that will strand vehicles at 6 a.m.

What is happening with VTA's electric bus charging?

VTA broke ground on the Cerone Microgrid Project at its Cerone Bus Division in September 2025. The microgrid includes 1.5 MW of rooftop solar PV plus 1 MW / 4 MWh of battery storage to support 35 battery-electric buses scheduled for 2026 delivery. It is a public example of the depot-microgrid architecture our team helps commercial fleet operators evaluate: generation and storage behind the meter, sized so the charging load does not set a punishing demand charge and does not wait on a distribution upgrade.

Which commercial EV charging contractors serve the Bay Area, and how do they differ?

Bay Area commercial EV charging contractors fall into three groups. First, regional C-10 electrical contractors who self-perform the customer-side design and installation; Cali Rollin Electric is in this group, with a Santa Clara County footprint. Second, national turnkey networks (Qmerit, FSG, and similar) that sell the program and subcontract local installation crews, which puts a layer between you and the people in the trench. Third, specialized fleet operators (Hallcon, for example) who build and run their own depots rather than serving third-party fleet customers. ChargePoint, headquartered here in Santa Clara County, is one of the EVSE manufacturers our team specifies and installs, alongside ABB, Wallbox, and FLO.

Get started

Fleet charging consultation

Tell us the facility address, vehicle counts by class, arrival dates, and dwell window. Send your site plan, single-line, panel schedules, or fleet rollout schedule and our team will come back with questions and a site-walk date. If you have a recent utility bill, include it; the demand history tells us more about your service than a photo of the gear.

  • Customer-side scope owned from meter to charger
  • Utility coordinated (PG&E, SVP, or CPAU)
  • OCPP-compatible EVSE with no network lock-in
  • C-10 #1144031 (California electrical contractor)
Call (408) 614-4451Free quote