Skip to main content
Federal EV charger tax credit expires June 30, 2026 — schedule your installation before it's gone. Call 408-614-4451

Your ADU Needs Its Own Electrical Service. We Install It Right the First Time.

An Accessory Dwelling Unit — detached or attached — requires a dedicated sub-panel, its own circuits, and separate metering in some cases. Most ADU projects in San Jose also benefit from a 240V EV charger rough-in while the walls are open. We handle the electrical scope from the main panel to the ADU, permit to final inspection.

Sub-panel required

For separate ADU service

EV rough-in

Add while walls are open

C-10 #1144031

Licensed CA electrician

Permit-required

All ADU electrical work

  • C-10 #1144031Licensed
  • Bonded& Insured
  • 15+ YearsExperience
  • Santa Clara CountyService Area

ADU Electrical Scope Items

What a Complete ADU Electrical Scope Covers

Every scope item below requires a permit in San Jose. We handle permit filing, inspection coordination, and delivery of permit close documentation.

Scope ItemTypical RequirementPermit Required
Sub-panel installation60–100A sub-panel at ADU from main panelYes
Feeder circuit to ADUSER cable or conduit run, sized per NEC 220Yes
ADU interior circuitsKitchen, bath, bedroom, living area circuitsYes
GFCI / AFCI protectionAll NEC 210.8 and 210.12 required locationsYes
EV charger rough-in240V / 50A conduit stub-out for future EVSEYes
Smoke / CO detectorsCRC-required placement in ADUYes
Separate meter (if required)CPUC / city requirement on some ADUsYes — utility coordination

Why Main Panel Comes First

Common issue

Main panel at capacity

ADU sub-panel cannot be added without headroom

We assess first

No surprises on install day

Main panel capacity confirmed before quoting sub-panel size

If an upgrade is needed, we scope both projects together — one permit process.

What to Budget

ADU Electrical Cost in San Jose

ADU electrical cost depends primarily on the feeder run distance from the main panel to the ADU. A short above-ground run on the same structure is the least expensive scenario. A long underground run to a detached ADU — requiring conduit trenching — adds significant cost and timeline.

Interior ADU electrical for a new construction 400–600 sq ft unit typically runs $6,000–$14,000 depending on circuit count and finish level. This includes all required GFCI and AFCI protection, smoke and CO detectors, and kitchen and bath circuit requirements.

The EV charger rough-in — a 240V/50A conduit stub-out — adds $500–$1,200 when done with the ADU electrical project. If you add it later, the cost is substantially higher because the walls are closed.

01

ADU Load Assessment

Sub-panel size, feeder route, and interior circuit requirements defined. Main panel capacity confirmed.

02

Permit Filing

Building permit (electrical sub-permit or standalone) filed. Rough-in inspection dates coordinated with general contractor.

03

Installation

Sub-panel, feeder, and interior circuits installed. EV rough-in stubbed if included.

04

Final Inspection & OPP

Final electrical inspection completed. Permit close documentation delivered. Utility meter coordination if required.

ADU Electrical Costs — Santa Clara County

ScopeRange
ADU sub-panel installation (60–100A, short run from main)$2,500 – $5,000
ADU sub-panel + feeder (long run, underground, or conduit)$4,000 – $9,000
ADU interior electrical (new construction — typical 400–600 sq ft)$6,000 – $14,000
EV charger rough-in (240V/50A conduit while walls are open)$500 – $1,200
Main panel upgrade (if required)$7,000 – $9,000
Permit (varies by SCC city)$500 – $1,000 depending on jurisdiction

Written quote provided before any work begins.

Get a Written Quote
ADU electrical work in Salinas, CA
ADU subpanel installation
Electrical rough-in for a new ADU build

Why Cali Rollin Electric

Main Panel First. Scope Right. No Surprises.

ADU electrical work gets complicated when the main panel is already near capacity, the feeder run is long, or the city requires separate metering. Our team assesses the main panel before quoting the ADU electrical scope — so the sub-panel size and feeder conductor are correctly specified from the beginning, not corrected on installation day.

C-10 #1144031. Full ADU electrical scope. Permit and inspection coordination included.

Common Questions

ADU Electrical FAQ

Does an ADU need its own electrical panel?

Yes — in virtually all cases an ADU requires a dedicated sub-panel. The most common approach is a sub-panel fed from the main home's panel, sized at 100–200A and installed in or near the ADU. This works for attached ADUs, garage conversions, and detached ADUs within about 100 feet of the main panel, provided the main panel has sufficient capacity to support both structures. A load calculation is always required to confirm this. For larger ADUs, ADUs more than 100–150 feet from the main panel, or when independent tenant billing is desired, a fully separate service with its own PG&E meter and main disconnect may be required. Cali Rollin Electric performs the load calculation during the free estimate to determine the right approach for your specific project.

Does an ADU need a separate utility meter?

No — California state law specifically prohibits local agencies from requiring a separate meter for ADUs under Government Code Section 65852.2. This was designed to reduce the financial barrier to ADU construction. In practice you have three options: a shared meter where the ADU runs off the main home's existing meter at no additional infrastructure cost, a sub-meter that tracks ADU usage privately for cost-splitting between owner and tenant, or a fully separate PG&E meter for independent utility billing. For rental ADUs the economics usually favor a separate meter — the upfront cost typically pays back in three to five years when the tenant pays their own utilities. Cali Rollin Electric navigates PG&E metering questions directly on your behalf.

Should I add an EV charger rough-in to my ADU electrical project?

Yes — and the cost argument is overwhelming. Adding EV rough-in during the ADU build costs roughly $500–$1,200 at Cali Rollin Electric — just the conduit stub, pull wire, and dedicated circuit reservation in the sub-panel. Adding a Level 2 charger later as a standalone project once walls are closed costs significantly more. Under the 2025 California Green Building Standards Code, new ADUs configured with attached private garages must be built EV-ready with conduit and panel capacity reserved for a future 240V EV charging circuit. Even when not strictly required, the ADU construction window is the cheapest possible moment to future-proof the parking space. Every ADU project Cali Rollin Electric handles includes this conversation before the rough-in inspection is scheduled.

How does ADU electrical permitting work in San Jose?

ADU permitting in San Jose is a multi-permit process coordinated through the San José Development Services Permit Center at SJPermits.org. The electrical permit for all ADU electrical work — sub-panel, wiring, circuits, and Title 24 compliance — is submitted as part of a larger ADU building permit package alongside building, plumbing, and mechanical permits under the 2nd Unit Added application type. Key San Jose requirements include an ADU Property Owner Declaration, an Address Assignment Request, a water and fire flow letter from the water company, and Title 24 energy compliance documentation using the 2025 California Building Standards Code. Plan submittal to permit approval typically takes two to three months. Cali Rollin Electric handles the electrical permit scope within this package and works directly with the general contractor and San Jose Building Division throughout the project.

Can you handle the entire ADU electrical scope or just the panel?

The entire electrical scope — from load calculation and permit drawings through final inspection sign-off. For ADU projects Cali Rollin Electric handles load calculation for the main home and ADU, electrical plan drawings for the permit package, trenching coordination for underground conduit to detached ADUs, sub-panel selection and installation, all branch circuit rough-in wiring, Title 24 and ESS-ready provisions, AFCI and GFCI protection throughout, EV charger rough-in at the parking location, rough-in and final inspection coordination, trim-out and panel labeling, and PG&E meter application coordination if a separate meter is desired. You do not need to manage separate electrical and panel contractors or translate between trades — Cali Rollin Electric works directly with your GC, ADU designer, and the San Jose Building Division.

Ready to get started?

Main panel assessment included. Written quote before any work begins. We coordinate directly with your GC.

Schedule a ConsultationCall 408-614-4451

Contact

Hours

Mon–Fri 7:00 AM – 4:00 PM

Emergency electrical services available 24/7

Schedule an ADU Electrical Consultation

We respond same day during business hours. We coordinate directly with your general contractor.

Starting an ADU Project? Get the Electrical Scope Right First.

Main panel assessment included. Written quote before any work begins. Permit and inspection coordination from rough-in through final.

Schedule an ADU Electrical Consultation

Or call directly: 408-614-4451

Service Area

ADU electrical installation across 12 cities in Santa Clara County

San JoseSanta ClaraSunnyvaleMountain ViewPalo AltoCupertinoLos GatosSaratogaCampbellMilpitasLos AltosLos Altos Hills
See full service area map →